By AJ Reis, CEO & founder of Future Energy Solar · Published November 17, 2026 · measured from our own project records
The short answer: for the Massachusetts homes we installed solar on from 2023 to 2026, the middle job took about 92 days from signed contract to the day the utility let the homeowner turn the system on in Eversource territory, and about 123 days with National Grid. The installation itself is usually one or two days; most of the time is paperwork and approvals.
These are not estimates. They are the dates recorded on our own job files for 242 homes Future Energy Solar installed in 2023–2026, measured step by step below.
How we measured it
- Every number is a median — the middle job — so one unusually slow or fast project does not pull it.
- Each step only counts jobs where both dates were recorded, so each row shows how many jobs it is based on.
- Dates are when the town or utility actually approved something, taken from our project records — not what we promised.
- No customer is identified. Towns appear only where we have at least three installs.
The steps, and how long each one took
| Step | Median | Jobs measured |
|---|---|---|
| Contract signed → town building permit approved | 46 days | 136 |
| Building permit applied for → approved | 11 days | 97 |
| Utility application → approval to install (Eversource) | 4 days | 55 |
| Utility application → approval to install (National Grid) | 48 days | 35 |
| Installed → permission to operate | 34 days | 75 |
| Contract signed → system on (Eversource) | 92 days | 80 |
| Contract signed → system on (National Grid) | 123 days | 44 |

1. Building permit from your town
After the contract, we design the system for your roof and file the building and electrical permits with your town. From signed contract to an approved building permit took a median of 46 days; once a permit application was in, towns approved it in a median of 11 days. Some towns review in a day or two; others take a few weeks.
2. The utility’s approval to connect
At the same time we apply to your electric utility to connect the system to the grid. This is where the two big Massachusetts utilities differ most in our records: Eversource gave approval to install in a median of 4 days (55 jobs), National Grid in a median of 48 days (35 jobs). The utility application has to be signed by the person whose name is on the electric account, so that signature is one of the few things that can hold up a project.
The first steps of that review have deadlines set by the state-approved interconnection rules: National Grid’s interconnection tariff (M.D.P.U. No. 1599) gives the utility 3 business days to confirm it received an application and 10 business days to say whether it is complete. The longer waits in our records come after that, while the utility reviews the connection itself. Eversource explains its side on its solar interconnection page.
3. Installation day
Our own crews install the system — no subcontractors. On a typical home that is one to two days on the roof and at the electrical panel.
4. Inspection and permission to operate
After the town’s final electrical and building inspections, the utility reviews the paperwork, may change or program the meter, and then grants permission to operate. From installation to permission to operate took a median of 34 days across 75 jobs. Only then should the system be switched on.
What a typical system looked like
The median system we installed was 12.9 kW with 29 panels (based on 209 jobs with the size recorded). The most common panel was the REC Alpha Pure-RX 460 W and the most common inverter the Enphase IQ8X microinverter. About 14% of homes added a battery.
By town: where we install most
Towns where Future Energy Solar has installed at least three systems in 2023–2026, with the median system size and the utility that serves those homes. Your own system is designed for your roof and your electric bill, so it can be larger or smaller than these. Tap a town name to see our page for that town, or see all the towns we serve.
| Town | Jobs | kW | Utility |
|---|---|---|---|
| Lexington | 20 | 14.7 | Eversource |
| Sharon | 9 | 13.5 | Eversource |
| Arlington | 8 | 8.4 | Eversource |
| Winchester | 8 | 12.2 | Eversource |
| Melrose | 7 | 11.6 | National Grid |
| Needham | 7 | 14.0 | Both |
| Acton | 6 | 12.4 | Eversource |
| Beverly | 6 | 10.8 | National Grid |
| Wakefield | 6 | 6.4 | Municipal |
| Westford | 6 | 12.0 | National Grid |
| Andover | 5 | 11.7 | National Grid |
| Medford | 5 | 8.7 | National Grid |
| Newton | 5 | 16.6 | Eversource |
| Stoneham | 5 | 12.7 | Eversource |
| Sudbury | 5 | 15.8 | Eversource |
| Chelmsford | 4 | 15.2 | National Grid |
| Framingham | 4 | 21.2 | Eversource |
| Haverhill | 4 | 11.4 | National Grid |
| Methuen | 4 | 6.8 | National Grid |
| Natick | 4 | 12.0 | Eversource |
| Salem | 4 | 8.7 | National Grid |
| Shirley | 4 | 12.9 | National Grid |
| Tewksbury | 4 | 10.1 | National Grid |
| Westwood | 4 | 15.6 | Eversource |
| Weymouth | 4 | 7.4 | National Grid |
| Woburn | 4 | 13.8 | Both |
| Billerica | 3 | 9.7 | National Grid |
| Boxford | 3 | 14.4 | National Grid |
| Chatham | 3 | 12.8 | Eversource |
| Malden | 3 | 15.7 | National Grid |
| Somerville | 3 | 8.5 | Eversource |
| Waltham | 3 | 12.9 | Eversource |
| Westborough | 3 | 15.6 | National Grid |
| Weston | 3 | 11.5 | Eversource |
What you can do to keep your project moving
- Have a recent electric bill ready — it sets the system size and the utility application.
- Make sure the person named on the electric account can sign the utility forms quickly.
- Answer the town’s inspection scheduling call or email promptly; inspections are booked with you.
- Tell us early about anything that changes the work — a new roof, a panel upgrade, an HOA rule.
Questions homeowners ask
Why does National Grid take longer than Eversource?
In our records the difference is almost entirely the utility’s review of the connection application before installation: a median of 48 days for National Grid against 4 days for Eversource. Your utility is set by your address, not chosen by you, and we file the application for you either way.
Can I use the system before permission to operate?
No. A grid-connected system must stay off until the utility grants permission to operate. Turning it on early can violate the interconnection agreement.
Does a battery add time?
A battery is installed at the same visit as the solar. It can add steps to the utility paperwork and the inspection, so plan the battery from the start rather than adding it later if you can.
Who measured this?
This page was written by AJ Reis, founder of Future Energy Solar, from the company’s own project records. Future Energy Solar is a local Massachusetts solar installer at 21 Olympia Ave, Unit V, Woburn, installing solar since 2015 with its own crews. We will update these numbers as more projects finish.